Per the Contractor: Ref: Plainfield Road paving:
As everyone is aware the milling and leveling on all affected streets will be completed by the end of this week July 26th.
The concrete work will begin on Wentworth July 30th.
We are scheduled to replace the catch basin in Silverton near Seiler's the week of August 5th.
Beginning Monday, July 29th we will begin the adjustments on the southern portion of the project in Silverton and work North into Deer Park. The adjustments should be completed by Wednesday.
We will begin final paving in Silverton Wednesday, July 31st and work North. The final paving in Silverton should be completed in 3 days. Upon the completion of paving in Silverton we will work to the North in Deer Park. The Deer Park paving is scheduled to be completed by August 22nd including Wentworth.