- The main portion of the project will be replacing the current roadway section between Lake and the railroad with new asphalt and curb. This will also include new concrete drive aprons in this section (from road to sidewalk), new storm sewer, and new ADA accessible curb ramps at the intersections. Sidewalk will be replaced in sections, as needed.
- The street between Plainfield and Lake will be resurfaced only.
- With the addition of curb on both sides of the roadway, parking will be limited to the north side of the street only once the project is completed.
- Duke Gas performed some service line and main line lowering ahead of the project. Our contractor is currently beginning on a water main replacement for the length of Oakwood, which is also part of the City project. Once this work is complete, the main roadway project will begin.
- The total project is tentatively scheduled to be completed this fall.