Upcoming Events
View All EventsLEGAL NOTICE
Notice of Public Hearings
City of Deer Park
The City of Deer Park will hold 2 public hearings: March 18, 2024 & April 1, 2024, both @ 6:30 pm, at the Deer Park Municipal Bldg., 7777 Blue Ash Rd, Deer Park OH 45236, for the purpose of hearing public comments on the City of Deer Park’s community development needs, and to discuss the possible submission of one or more Community Development Block Grant (CDBG) applications for the 2024 program year.
DEER PARK BOARD OF ZONING APPEALS
==========================================================
NOTICE OF PUBLIC HEARING and MEETING
Ohio Revised Code Section 121.22 (F)
The Board of Zoning Appeals of the City of Deer Park, Ohio shall meet on Monday, the 8th day of April, 2024, at SIX P.M., in the City Council Chambers of the Deer Park Municipal Building, located at 7777 Blue Ash Rd, Deer Park, Ohio.
Latest News
View All NewsOAKWOOD STREET PROJECT UPDATE
- The main portion of the project will be replacing the current roadway section between Lake and the railroad with new asphalt and curb. This will also include new concrete drive aprons in this section (from road to sidewalk), new storm sewer, and new ADA accessible curb ramps at the intersections. Sidewalk will be replaced in sections, as needed.
- The street between Plainfield and Lake will be resurfaced only.
- With the addition of curb on both sides of the roadway, parking will be limited to the north side of the street only once the project is completed.
- Duke Gas performed some service line and main line lowering ahead of the project. Our contractor is currently beginning on a water main replacement for the length of Oakwood, which is also part of the City project. Once this work is complete, the main roadway project will begin.
- The total project is tentatively scheduled to be completed this fall.
PLAINFIELD ROAD CONSTRUCTION
Everything has been pushed out due to boring under the railroad tracks (this is an eight-week project) and concrete work is being reschedule as well during this same time.
NEW Target date is now June 24,2024 for paving. Construction Schedules are a fluid situation.
Below is the schedule provide below.
- Complete watermain related work and concrete restoration in Silverton on Plainfield between Blue Ash Rd and Montgomery by 3/14/24.
- Complete watermain related work on Deer Park Ave by 3/21/24
- Begin catch basin repair/replacement 3/18/24 this work will take approximately 2 weeks. This work will begin in Silverton and head north.
- Begin permanent sod area restoration 3/19/24 in Silverton and head north. This work will take approximately 3 weeks.
- Begin permanent concrete restoration 3/25/24 in Silverton and head north. This work will take approximately 6 week.
- Begin bore pit excavation 4/29/24.(the bore contractor has adjusted his schedule) The bore and subsequent water main work on Plainfield between Webster and the train tracks will take approximately 8 weeks.
- Begin permanent asphalt restoration 6/24/24.
OAKWOOD AVENUE STREET IMPROVEMENT PROJECT FYI
The Oakwood Avenue Street Improvement project will start in full swing starting Monday March 11, 2024; starting with saw cutting, additional digging for water line replacement, and then reconstruction of the street.